Task
  Name | 
Duration | 
Start | 
Finish | 
Predecessors | 
| 
Task 1 | 
2 days | 
Sun 2/4/18 | 
Mon 2/5/18 | |
| 
Task 2 | 
5 days | 
Sun 2/4/18 | 
Thu 2/8/18 | |
| 
Task 3 | 
3 days | 
Fri 2/9/18 | 
Tue 2/13/18 | 
2 | 
| 
Task 4 | 
7 days | 
Tue 2/6/18 | 
Wed 2/14/18 | 
1 | 
| 
Task 5 | 
11 days | 
Tue 2/6/18 | 
Tue 2/20/18 | 
1 | 
| 
Task 6 | 
5 days | 
Thu 2/15/18 | 
Wed 2/21/18 | 
2,4 | 
| 
Task 7 | 
9 days | 
Wed 2/14/18 | 
Mon 2/26/18 | 
3 | 
| 
Task 8 | 
5 days | 
Thu 2/22/18 | 
Wed 2/28/18 | 
3,6 | 
| 
Task 9 | 
7 days | 
Thu 2/15/18 | 
Fri 2/23/18 | 
4 | 
| 
Task 10 | 
3 days | 
Wed 2/21/18 | 
Fri 2/23/18 | 
5 | 
| 
Task 11 | 
15 days | 
Tue 2/27/18 | 
Mon 3/19/18 | 
7 | 
| 
Task 12 | 
6 days | 
Thu 3/1/18 | 
Thu 3/8/18 | 
8 | 
| 
Task 13 | 
7 days | 
Mon 2/26/18 | 
Tue 3/6/18 | 
9,10 | 
| 
Task 14 | 
12 days | 
Tue 2/27/18 | 
Wed 3/14/18 | 
7 | 
| 
Task 15 | 
16 days | 
Fri 3/9/18 | 
Fri 3/30/18 | 
12,13 | 
Sunday, February 11, 2018
Precedence Diagrams
I really enjoyed this week's topic of precedence diagramming.  I learned how to do a forward pass and a backward pass to determine the slack/float of a project and how to determine the critical path of a project in an optimistic, most likely, or least likely time frame.  I used Microsoft Project to assist me with the WBS, AON and Gantt charts.  However, I did the precedence diagrams by hand as you can see, below.  I look forward to hearing from the professor to see if I arrived at the critical path and end dates correctly.
 