Precedence Diagrams

I really enjoyed this week's topic of precedence diagramming.  I learned how to do a forward pass and a backward pass to determine the slack/float of a project and how to determine the critical path of a project in an optimistic, most likely, or least likely time frame.  I used Microsoft Project to assist me with the WBS, AON and Gantt charts.  However, I did the precedence diagrams by hand as you can see, below.  I look forward to hearing from the professor to see if I arrived at the critical path and end dates correctly.

Task Name
Duration
Start
Finish
Predecessors
Task 1
2 days
Sun 2/4/18
Mon 2/5/18
Task 2
5 days
Sun 2/4/18
Thu 2/8/18
Task 3
3 days
Fri 2/9/18
Tue 2/13/18
2
Task 4
7 days
Tue 2/6/18
Wed 2/14/18
1
Task 5
11 days
Tue 2/6/18
Tue 2/20/18
1
Task 6
5 days
Thu 2/15/18
Wed 2/21/18
2,4
Task 7
9 days
Wed 2/14/18
Mon 2/26/18
3
Task 8
5 days
Thu 2/22/18
Wed 2/28/18
3,6
Task 9
7 days
Thu 2/15/18
Fri 2/23/18
4
Task 10
3 days
Wed 2/21/18
Fri 2/23/18
5
Task 11
15 days
Tue 2/27/18
Mon 3/19/18
7
Task 12
6 days
Thu 3/1/18
Thu 3/8/18
8
Task 13
7 days
Mon 2/26/18
Tue 3/6/18
9,10
Task 14
12 days
Tue 2/27/18
Wed 3/14/18
7
Task 15
16 days
Fri 3/9/18
Fri 3/30/18
12,13